Evoqua United States - Canada - EN

Providing a System with Budget and Schedule Constraints

Evoqua works with a tight budget and delivery requirements to provide a system that met the semiconductor fab needs

Challenge

This semiconductor fab was challenged with a tight budget and an accelerated project schedule to meet production needs.

 

Solution

The original bid for this job included a new UPW system with turnkey services, however the final project required Evoqua Water Technologies to utilize existing equipment supplied in a building that was being shut down. The challenge was to reinstall this equipment at another site with a very tight turn around.

Evoqua supplied additional filters, UV sterilizers, pumps, and refurbishment of the existing equipment that was necessary to meet water quality requirement for the building, as well as provide a guaranteed system. The complete system includes pretreatment, reverse osmosis, service deionization, UVs and polishing filters.

Evoqua provided installation supervision services with the relocation and installation work being contracted directly with the customer.

Results

This project is a good example of how Evoqua Water Technologies can work within a customer’s tight budget and delivery requirements while still providing a system that meets their needs.

星空彩票外围权威网站_APP下载_安卓版/苹果版下载_(2024)_最新版 星空彩票真人权威公司_APP下载_安卓版/苹果版下载_(2024)_最新版 kaiyun·开云综合体育(官方)最大知名买球_APP下载_安卓版/苹果版下载_(2024)_最新版 开云综合体育(官方)真人网上盘口_APP下载_安卓版/苹果版下载_(2024)_最新版 最新靠谱kaiyun·开云综合体育(官方)导航_APP下载_安卓版/苹果版下载_(2024)_最新版 星空彩票靠谱体育盘口_APP下载_安卓版/苹果版下载_(2024)_最新版 靠谱风云(官方)足球入口_APP下载_安卓版/苹果版下载_(2024)_最新版 博鱼(官方)知名最火网_APP下载_安卓版/苹果版下载_(2024)_最新版 leyu·乐鱼综合体育(官方)最大外围官方_APP下载_安卓版/苹果版下载_(2024)_最新版 IM体育最新网上评级_APP下载_安卓版/苹果版下载_(2024)_最新版