Evoqua United States - Canada - EN

Coal Power Utility Meets Updated CCR Regulations

A fossil-fueled power facility met updated Coal Combustion Residual (CCR) regulations prior to a deadline, and met all requirements.

case-study-heavy-power-plant-ccr-reqs.jpg

Problem

Updated State and Federal environmental regulations led to a shortened project timeline for a facility that needed a Low Volume Wastewater (LVWW) system. The State maintained a pending deadline related to the closure of ash impoundments. Because the regulation prevented the use of the ash impoundment after the deadline, the facility needed to divert all low volume wastewater flows entering the impoundment from the deadline date to the time a permanent LVWW system could be installed and operational.

Evoqua worked closely with the client on a very compressed time line and also provided a complete temporary LVWW system while an area for the permanent system was prepared. Evoqua sourced equipment and ramped up production to deliver the permanent system 30 days before the deadline, avoiding National Pollutant Discharge Elimination System (NDEPS) permit-related fines.

 

Background

The CCR Rule became effective on 10/19/2015 and set a federal standard for the safe disposal of coal ash. The rule establishes technical requirements for CCR landfills and surface impoundments that were challenged legally and politically. These challenges resulted in uncertainty delaying project execution. The methodical pace to resolve the uncertainties left Utility Companies in a predicament of needing to both comply with regulations and continue to generate electricity.

In this instance, the plant reached out to Evoqua - an existing provider - for a solution that would be in place between the deadline date and the completion of permanent system.

 

Solution

With a very short design time Evoqua proposed, and provided the customer a complete temporary LVWW system that included: ballasted clarification, chemical addition and inventory management, solids dewatering, and around the clock equipment operation. The system was designed to treat 10,000 gpm effluent to the regulated outfall. The system achieved all NPDES permitted requirements without issue. TSS levels were reduced from an average of 400 ppm to less than 20 ppm. All requirements for metals, such as Arsenic and Mercury were met.

 

Results

The customer embarked on a month-long excavation project running 24/7 to make way for the permanent system’s installation. Evoqua successfully accelerated the production of equipment to provide the full capacity 30 days before the regulatory deadline. The operational staff ramped up to provide the personnel for continuous operation of the system. The system successfully treated over one billion gallons of wastewater under the permit specifications within the first six months of the project.

Once the need for the system was replaced by the permanent LVWW system, the temporary equipment was scaled down, and the system transitioned to treat the water in the ash impoundment once the impoundment closure was initiated. The permanent LVWW system started up flawlessly and continues to meet all design and discharge requirements.

星空彩票外围权威网站_APP下载_安卓版/苹果版下载_(2024)_最新版 星空彩票真人权威公司_APP下载_安卓版/苹果版下载_(2024)_最新版 kaiyun·开云综合体育(官方)最大知名买球_APP下载_安卓版/苹果版下载_(2024)_最新版 开云综合体育(官方)真人网上盘口_APP下载_安卓版/苹果版下载_(2024)_最新版 最新靠谱kaiyun·开云综合体育(官方)导航_APP下载_安卓版/苹果版下载_(2024)_最新版 星空彩票靠谱体育盘口_APP下载_安卓版/苹果版下载_(2024)_最新版 靠谱风云(官方)足球入口_APP下载_安卓版/苹果版下载_(2024)_最新版 博鱼(官方)知名最火网_APP下载_安卓版/苹果版下载_(2024)_最新版 leyu·乐鱼综合体育(官方)最大外围官方_APP下载_安卓版/苹果版下载_(2024)_最新版 IM体育最新网上评级_APP下载_安卓版/苹果版下载_(2024)_最新版